Pentaho ETL
|
Prerequisites
To be able to set this flag, users will need the following role assigned to them:
- Policy Role - System Administrator’
|
ETL Process Locked
Whenever an ETL process is initiated, either manually or via a schedule, the flag and locked time will be set automatically by the system. Once the ETL process has finished, the flag will be removed and the locked time cleared.
This flag is used to prevent that more than one ETL process can run at a time.
To view the current Status of the flag, navigate:
- From the menu, select Admin Tools Pentaho ETL.
- ONLY change the value manually for very limited reasons. For example
- Change from CHECKED to UNCHECKED if you are certain that the ETL process has finished, but the flag was not cleared.
- Change from UNCHECKED to CHECKED if you want ETLs from being performed. ETL will only run again once you UNCHECK the flag again.
|